WORK-PHASES
first published: 25.07.2013
June 2013
Kick off – 3 days:
Preparatory meeting of artistic directors and project managers of all participating institutions in Lisbon
August 27th to Sept.2nd
Launching phase – 5 days:
Workshop with all participants (scientists and performers); lectures, film projections, workshops in Cologne
Sept 2013 – February 2014
Research phase – 4 x 10 days:
Research phase of each group in the four participating countries; first rehearsals and public presentation of interim results, e.g. podium discussions or photo exhibitions
April 2014
Rehearsal phase – 20 days:
Rehearsal phase of each group in the facilities of the participating cities; work-in-progress performances, discussions with the audience
May 2014
Final phase – 15 days:
Final rehearsal and performance phase; Premieres of the four different performances during the Sommerblut Festival in Cologne; discussions with the audience
September 2014
Coming home phase – Performances and art installations in the participating cities
October 2014
Follow-up meeting – 2 days: Follow up and evaluation meeting of artistic directors and project managers of all participating institutions